South Lodge

Works are progressing well on site with Phase 1 works nearly completed.

The Main House roof has been built and internal works to the second floor are currently underway, with partitions being erected.

The staff house demolition works and roof has also been completed and the steel structure to the ground floor has been installed.

The study’s oak structure is currently being installed and the elderly parents house has seen substantial progress with walls and roof now complete.

The landscaping has also progressed with several trees planted and all of the paths on the rear garden laid.

The contractors are currently working on the mechanical and electrical installations to the main house and works on the pool house steel structure will be commencing next month.

 

Project Architect:    Marianne Fischer-Bee

Contractor:             Seacon Ltd

Completion Date:   Fourth Quarter 2017