Gilston I

External Façade restoration is almost complete –  new decorative mouldings, windows, render.

Internal services such as Air Conditioning, underfloor heating, state of the art AV are all installed.

The internal walls and linings are currently being installed in preparation for new cornices, skirting’s, architraves and new decorative.

Solid Portland Stone cantilevered staircase currently in production of site to be installed in the next month.

 

Project Leader:                 Gemma McCloskey

Contractor:                         Seacon Ltd

Completion Date:             Third Quarter 2017