The contractors Knight Build Ltd are now on the final stage of works and completion of phase 1, ahead of the programme anticipated completion date of April 2017.

The Basement structure and Undercroft have been completed showing a good size footprint. The replacement of the roof is almost complete with the lead finish currently being installed and all detailing being finished to mirror the original roof.

In the next couple of months works on rebuilding part of the rear façade will begin once the temporary roof and perimeter scaffolding has been struck.

Once all phase 1 works are complete the preparation for Phase 2 handover to the new contractor will commence.

 

Project Architect:        Anna Saroukhanova

Contractor:                  Knight Build Ltd

Completion Date:        Third Quarter 2017